Skip to main content

Sizing

References

1. Enter the desired amount of product to inject per volume of water as a percentage
e.g. 1 gallon of product per 100 gallons of water = 1 %

2. Enter the Well Pump Output (GPM) or Max System Flow Rate (GPM)

Support
  • Technical Support
  • techsupport@stenner.com
  • 800-683-2378
Key
  • PPM - Parts Per Million
  • GPD - Gallons Per Day
  • GPM - Gallons Per Minute
  • PPG - Pulse Per Gallon

Dosage Required (using oxidative rates) source: Table 8-2, Chapter 8, “Residential Water Processing”, Water Quality Association, Lisle, IL., 2000.

Metering Pump Output source: Page 120, Chemical Feed Information, USA Bluebook Operator’s Companion, 6th Edition.


3. Select the pump’s max. flow rate output. Reference the chart

Flow Rate Outputs 80 psi max
Econ FP | Econ Integrator™
Item Number Prefix
Maximum
GPD
E10PLM | E10RLM 0.49
E10PHM | E10RHM 0.83
E20PHM | E20RHM 1.41
E20PHF | E20RHF 4.5
E20PHG | E20RHG 16.0
E20PHH | E20RHH 30.0
Flow Rate Outputs 100 psi max
S10P
Item Number Prefix
Maximum
GPD
S3P01 5.0
S3P02 17.0
S3P06 30.0

4. Select the water meter PPG. Reference the chart.

Must select values in Steps 1-3
Must select values in Steps 1-3

IMPORTANT: If the Injection Time is greater than the Available Dose Time, select a pump with a higher GPD and repeat 2-4.

 

Plastic Meters
Size PPG Item Number
3/4" 1 JLP0750-1PPG
3/4" 2 JLP0750-2PPG
3/4" 4 JLP0750-2PPG
3/4" 10 JLP0750-10PPG
1" 1 JLP1000-1PPG
1" 2 JLP1000-2PPG
1" 4 JLP1000-4PPG
1.5" 1 JLP1500-1PPG
1.5" 2 JLP1500-2PPG
1.5" 4 JLP1500-4PPG
Stainless Steel Meters
Size PPG Item Number
2" 1 MNLRS20-1PPG
2" 2 MNLRS20-2PPG
2" 4 MNLRS20-4PPG

5a. In the pump’s Seconds mode, select a maximum operating time that is greater than or equal to the injection time calculated in 4.

5b. Calculate the percentage the injection time is of the maximum operating time selected in 4a.

x% = injection time/max. operating time x 100

The injection time cannot be less than 10% of the pump’s maximum operating time.